Contract awardedPumping stations and small treatment plants

West Cannock mine water pumping test and treatment goes to JN Bentley

The Mining Remediation Authority hired JN Bentley to run a three-month pumping test on its borehole in the West Cannock coalfield. The results will shape how the authority manages rising mine water across the Cannock coalfield in the long term.

Early samples from two boreholes found zinc too high to release untreated into the local watercourse or sewers. JN Bentley must therefore treat the water in a temporary plant, taking out iron, zinc and suspended solids to meet the environmental permit. Treated water, up to 10 litres a second, then runs to a nearby watercourse through overland pipes and a disused culvert.

The technical score counted for 70% and cost for 30%. Three bids came in. JN Bentley won in August 2026 at £1.6m, above the £1.2m estimate, and the contract runs to September 2027.

Alert me to similar tenders

Contract ends September 2027

What
Pumping stations and small treatment plants
Supplier
JN Bentley
Value
£1.58m
How it was bought
Open procedure
3 bids
Dates and next
Sep 2026 to Sep 2027

How it was bought

3 official notices
  1. 10 Mar 2026Tender noticeFind a Tender
  2. 18 Mar 2026Tender re-issuedFind a Tender
  3. 8 Apr 2026Bids closed3 bids
  4. 25 Aug 2026Award noticeFind a Tender
  5. 14 Sep 2026Contract starts
  6. 13 Sep 2027Contract ends

Mining Remediation Authority has bought this 12 or more times since 2021

Last bought
Oct 2026
Typical length
1 year
Typical value
£472,435
Suppliers used
12
in its last 12 purchases
AwardedContractWon byValue
Oct 2026Locked2 yearsLocked£482,030
Aug 2026This purchase1 yearJN Bentley£1.58m
Jul 2026LockedLocked£186,002
Jun 2026Locked4 monthsLocked£47,524
Dec 2025Locked8 yearsLocked£203.1m

and at least 7 more

Suppliers Mining Remediation Authority has used in its last 12 purchases

SupplierContractsValue
JN Bentley Won this one2£2m
Locked1£203.1m
Locked1£4.69m
Locked1£1.02m
Locked1£482,030

and 7 more

See the contracts and who won them

Figures to 21 November 2026

How it compares

With every pumping stations and small treatment plants award since 2021

Half of awards fall between £51,126 and £320,610Median £111,594

Awards
266
Firms that won them
149
Median award
£111,594
of 255 with a value
This award
Bigger than 91%
of them
Typical length
8 months
In West Midlands
18 awards

JN Bentley ranks 9th of 149 firms for pumping stations and small treatment plants awards since 2021.

RankFirmAwardsValue
1Locked17£6.07m
2Locked8£9.22m
2Locked8£523,369
2Locked8£371,937
5Locked7£2.7m
6Locked6£911,789
9JN Bentley Won this one4£6.03m
See who wins this work

Pumping stations and small treatment plants at other buyers

Mining Remediation Authority has awarded 182 contracts since 2021.

See Mining Remediation Authority's page
  • JN Bentley has won 21 public contracts since 2021, 4 of them from Mining Remediation Authority.

    • Aug 2026This purchase£1.58m
    • Sep 2021Locked£410,293
    • Jul 2021Locked£293,998
    • May 2021Locked£85,960
    See the contracts

1 pumping stations and small treatment plants tender is open now

See it
More pumping stations and small treatment plants contracts awarded in 2026