Particle Containment Facility rewiring for MOD goes to Tower Electrical
- Ministry of Defence
- South West
- Direct
- 11 November 2025 to 31 March 2026
The Ministry of Defence hired Tower Electrical Essex Limited to rewire the low voltage supply to the Particle Containment Facility (PCF) and Building F6.
The work was to bring that infrastructure up to current safety standards. The contractor was also to take the hazardous, unsupported system in Building F3 out of use.
The MOD awarded the £84,234 contract directly. Work started in November 2025 and was due to end in March 2026.
- What
- Electrical installation, rewiring and repairs
- Buyer
- Ministry of Defence
- Supplier
- Tower Electrical Essex Limited
- Value
- £84,234
- How it was bought
- Direct
- Dates and next
- Nov 2025 to Mar 2026