The Ministry of Justice (MoJ) hired Wates to design and build rapid deployment cells at HMPPS Albany.
The cells were standalone container units, each for one risk-assessed prisoner and fitted with fixed furniture. They could stand on one or two storeys and link to sleeper units and ancillary space such as kitchens, laundries and offices. Wates also had to lay foundations and hard standing and connect power, water, drainage and fire alarms.
The work was let as a two-stage design and build contract under PPC2000. Its first stage, pre-construction surveys and design, cost £545,602. The MoJ ordered the work as a call-off from a framework agreement. The £14,797,848 contract was due to end in June 2026.
- What
- Modular and portable buildings
- Buyer
- Ministry of Justice
- Supplier
- Wates
- Value
- £14.8m
- How it was bought
- Call-off from a framework agreement
- Dates and next