Galliford Try builds Rapid Deployment Cells at HMPPS Deerbolt for the MoJ
- Ministry of Justice
- North East
- Call-off
- 23 June 2025 to 26 June 2026
The Ministry of Justice ordered Rapid Deployment Cells (RDC) for HMPPS Deerbolt from Galliford Try, through the MoJ Constructor Services Framework.
The cells were self-contained container units, each for one risk-assessed prisoner, set out over one or two storeys with fixed furniture. Support buildings such as offices, laundries and kitchens sat alongside. The works also covered foundations, drainage and connections for power, water, the fire alarm and in-cell telephones.
Galliford Try was to design and build the cells in two stages. The award was £14,790,799, for work that began in June 2025 and was due to end in June 2026.
- What
- Modular and portable buildings
- Buyer
- Ministry of Justice
- Supplier
- Galliford Try
- Value
- £14.8m
- How it was bought
- Call-off, MoJ Constructor Services Framework
- Dates and next
- Jun 2025 to Jun 2026