The Mining Remediation Authority (MRA) needed a replacement buoy for the outfall of its mine water treatment scheme at Whitburn. The authority built the scheme to control mine water that had been steadily rising. The outfall lies about 1km from bathing beaches on the North Sea.
Seaserve Limited supplied the new buoy and mooring with all their fixings, and installed them with the help of divers. The work had to meet current safety law in full.
The MRA awarded the £36,316 contract to Seaserve directly. It ran from September 2025 and was due to end in November 2025.
- What
- Aids to navigation, buoys and moorings
- Supplier
- Seaserve Limited
- Value
- £36,316
- How it was bought
- Limited
- Dates and next
- Sep 2025 to Nov 2025