Heligan Gardens studies a Forest Enterprise Hub for the National Forest
- The National Forest Company
- East Midlands
- Open
- 9 January 2026 to 31 March 2026
The National Forest Company (NFC) hired Heligan Gardens Limited to test the case for a Forest Enterprise Hub in the Heart of the National Forest.
The study ran in two phases, and the second depended on what the first found. Phase 1 set out the case, drawing on need, demand and ambition, to shape a concept for the hub. Phase 2 was to build an outline business case. It was to weigh site design options and sustainability features alongside the hub's facilities, its commercial income and a financial appraisal.
Bids were scored on methodology and expertise at 30% each, value for money at 20%, and understanding of the brief and fit with the National Forest's ethos at 10% each. The NFC ran an open tender, and the £64,960 contract was due to end in March 2026.
- What
- Feasibility studies and options appraisals
- Supplier
- Heligan Gardens Limited
- Value
- £64,960
- How it was bought
- Open
- Dates and next
- Jan 2026 to Mar 2026