Max Fordham designs building services for the National Gallery's new wing
- National Gallery
- London
- Competitive flexible procedure, 5 bids
- 22 June 2026 to 31 August 2033
Max Fordham won the mechanical, electrical and public health (MEP) design for the National Gallery's new wing at about two-thirds of the estimate.
The wing is on Trafalgar Square, and Max Fordham's role covers RIBA stages 1 to 7. The firm must tie the new building services into the gallery's existing ones around live operations, and advise on planning and heritage approvals where needed. During construction it reviews contractor design, supports commissioning and sign-off, and helps with handover, soft landings and defects.
Five firms bid, and each was judged on its technical response, social value, resource schedule and fee schedule. The £1,804,000 award came in June 2026, and the contract runs to August 2033.
Contract ends August 2033
- What
- Building services (M&E) engineering design
- Buyer
- National Gallery
- Supplier
- Max Fordham
- Value
- £1.8m
- How it was bought
- Competitive flexible procedure
- 5 bids
- Dates and next
- Jun 2026 to Aug 2033