Tripod Crest resurfaces the A14 between junctions 36 and 38
- National Highways
- East of England
- Call-off
- 20 November 2025 to 26 December 2025
National Highways ordered resurfacing and drainage work on the A14 from Tripod Crest through the Pavement Delivery Framework (PDF). The work covered resurfacing between junctions 36 and 38 and drainage work on the same stretch, with further work between junctions 38 and 42.
The one-month call-off was worth £1.8m. It started in November 2025 and was due to end in December 2025.
- What
- Carriageway resurfacing, patching and reconstruction
- Buyer
- National Highways
- Supplier
- Tripod Crest
- Value
- £1.81m
- How it was bought
- Call-off, PDF
- Dates and next
- Nov 2025 to Dec 2025