DBFO handback assurance for National Highways goes to WSP
- National Highways
- Call-off from a framework agreement
- 1 December 2024 to 31 March 2028
National Highways hired WSP to check that eight Design Build Finance and Operate (DBFO) contracts from Tranche 1 and 1A meet their handback requirements as they near expiry. Assurance on them began in October 2016.
WSP carries the work on from an earlier consultant task. Because the contracts' timescales are fixed, the handover had to keep the national approach steady.
The £12.8m call-off from a framework runs from December 2024 to March 2028.
Contract ends March 2028
- What
- Commercial, contract management and PFI advice
- Buyer
- National Highways
- Supplier
- WSP
- Value
- £12.8m
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Dec 2024 to Mar 2028