National Grid diverts its 4YN route in Kent for the Lower Thames Crossing
- National Highways
- South East
- Direct award
- 21 August 2026 to 31 March 2031
National Highways is paying National Grid Electricity Transmission PLC to divert National Grid's 4YN transmission route so the Lower Thames Crossing road can be built. The agreement covers the works on Kent roads. Besides the diversion itself, it takes in surveys, enabling works and consents.
National Highways first estimated the work at £26.1m. It awarded the contract directly in June 2026 at £39,563,014, more than one and a half times that estimate. The contract runs to March 2031.
Contract ends March 2031
- What
- Electricity network works and connections
- Buyer
- National Highways
- Value
- £39.6m
- How it was bought
- Direct award
- Dates and next
- Aug 2026 to Mar 2031