M5 Wynhol & Tickenham ground investigation goes to BAM Nuttall
- National Highways
- South West
- Call-off from a framework agreement
- 20 February 2026 to 31 December 2026
National Highways ordered ground investigation on the M5 at Wynhol and Tickenham from BAM Nuttall.
The same order covers phase 1 of the preliminary design for rock anchors at Wynhol. The work pairs a geotechnical assessment of the ground with engineering design to keep the infrastructure stable.
BAM Nuttall took the call-off under a framework agreement in February 2026. The £984,664 contract runs to December 2026.
Contract ends December 2026
- What
- Ground investigation
- Buyer
- National Highways
- Supplier
- BAM Nuttall
- Value
- £984,664
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Feb 2026 to Dec 2026