Contract awardedGround investigation
Dwr Cymru digs trial holes at Rogerstone for Natural Resources Wales
- Natural Resources Wales
- Wales
- Direct
- 19 January 2026 to 1 March 2026
Natural Resources Wales hired Dwr Cymru Cyfyngedig to dig trial holes at Rogerstone. The digging was meant to check ground conditions and map utilities, with a report to inform later infrastructure planning.
Natural Resources Wales awarded the work directly. The £46,407 contract started in January 2026 and was due to end in March 2026.
- What
- Ground investigation
- Supplier
- Dwr Cymru Cyfyngedig
- Value
- £46,407
- How it was bought
- Direct
- Dates and next
- Jan 2026 to Mar 2026