The Nuclear Decommissioning Authority (NDA) hired Amentum Clean Energy to review the literature on zirconolite and HIP for plutonium disposition. HIP is hot isostatic pressing. The review was to trace the history of both, drawing on past technical work in the nuclear sector.
The NDA placed the work as a call-off under a framework agreement. The £104,246 contract ran from February 2026 and was due to end in November 2026.
- What
- Evidence reviews and literature reviews
- Supplier
- Amentum Clean Energy
- Value
- £104,246
- How it was bought
- Call-off from a framework agreement
- Dates and next