Database appliances for Network Rail's data centres come from Oracle
- Network Rail Infrastructure Limited
- London
- Direct
- 6 January 2026 to 25 November 2026
Network Rail Infrastructure Limited bought two high-performance database appliance systems from Oracle for two of its data centre locations.
Oracle supplies the hardware and software, installs and configures the appliances, and gives technical support. The work includes fitting the systems into Network Rail's existing infrastructure.
Network Rail awarded the £1,034,949 contract directly. It runs from January 2026 to November 2026.
- What
- Servers and storage
- Supplier
- Oracle
- Value
- £1.03m
- How it was bought
- Direct
- Dates and next
- Jan 2026 to Nov 2026