McLaughlin & Harvey wins Nexus's North Shields ferry landing relocation
- NEXUS
- North East
- 3 bids
- 11 April 2025 to 30 June 2027
Nexus hired McLaughlin & Harvey to relocate the North Shields ferry landing, designing and building a new one and clearing the old site. The contractor is responsible for consents as well as design and construction. The new landing includes a pontoon, linkspan and bank seat, along with work on land.
The old landing's redundant structures come out, and the Fish Quay's protection jetty is extended. Changes to the Western Quay give the public access and make room for utility routes. The work runs in two stages. The first covers planning before work starts, early works and detailed design, and the second the rest of the build.
Three firms bid, and quality carried 60% of the marks against 40% for price. McLaughlin & Harvey's contract was worth £23.9m over 26 months.
Contract ends June 2027
- What
- Harbour, marine and mooring works
- Buyer
- NEXUS
- Supplier
- McLaughlin & Harvey
- Value
- £23.9m
- How it was bought
- Not published
- 3 bids
- Dates and next
- Apr 2025 to Jun 2027