ARCs environmental impact assessment for NHSBT goes to Eunomia
- NHS Blood and Transplant
- Open procedure (below threshold)
- 30 April 2026 to 31 October 2026
NHS Blood and Transplant hired Eunomia Research & Consulting to assess the environmental impact of its Assessment and Recovery Centres (ARCs) programme.
Eunomia's job was to work out the programme's effects on the environment and advise on meeting regulatory and sustainability standards.
After an open tender that small businesses could enter, the £72,000 contract went to Eunomia, itself a small business, in April 2026. The work was due to end in October 2026.
- What
- Environmental impact assessment
- Value
- £72,000
- How it was bought
- Open procedure (below threshold)
- Dates and next
- Apr 2026 to Oct 2026