Fullwell Cross gets a bigger power supply from UK Power Networks
- NHS Property Services Limited
- London
- Direct
- 5 January 2026 to 6 March 2026
NHS Property Services hired UK Power Networks to upgrade the electrical intake at the Fullwell Cross site. The upgrade was enabling work, needed before air source heat pumps could be installed there. The heat pumps were expected to raise the site's power demand, so the intake's capacity had to grow first.
The work was awarded directly, without a tender. The £26,841 contract ran from January 2026 and was due to end in March 2026.
- What
- HV and LV distribution, switchgear and substations
- Supplier
- UK Power Networks
- Value
- £26,841
- How it was bought
- Direct
- Dates and next
- Jan 2026 to Mar 2026