Abbeycom replaces the outpatient flooring at St. Margarets Hospital
- NHS Property Services Limited
- North West
- Limited
- 23 March 2026 to 8 May 2026
NHS Property Services hired Abbeycom Limited to replace the flooring in the outpatient department at St. Margarets Hospital in Greater Manchester. The old floor was to come up and new flooring go down in a clinical area.
Abbeycom took the £95,695 contract without an open tender. Work started in March 2026 and was due to finish in May 2026.
- What
- Flooring supply and installation
- Supplier
- Abbeycom Limited
- Value
- £95,695
- How it was bought
- Limited
- Dates and next
- Mar 2026 to May 2026