Sulzer fits a standby generator connection at NLB's Oban base
- Northern Lighthouse Board
- Scotland
- Open, 4 bids
- 19 January 2026 to 30 January 2026
Northern Lighthouse Board hired Sulzer to fit a connection point for a standby diesel generator at its Oban base.
The point let NLB plug in a generator by hand and keep the base powered through a mains failure or blackout. It was mounted on the exterior of the ESTF Building and cabled on tray to the low-voltage switchboard in the switch room. The 400A breaker it fed into had to be turned round in place, because its protection device was not bi-directional.
Four firms bid after a mandatory site visit, with capability and project information worth 70% of the score and price 30%. Sulzer's £43,543 job was due to be done in January 2026.
- What
- Standby generators and UPS
- Supplier
- Sulzer
- Value
- £43,543
- How it was bought
- Open
- 4 bids
- Dates and next
- Jan 2026 to Jan 2026