Process Decontamination Systems runs VP Chemical Testing Phase III for NNL
- National Nuclear Laboratory
- North West
- Below threshold - without competition
- 30 April 2026 to 31 March 2027
National Nuclear Laboratory hired Process Decontamination Systems Limited to carry on developing vapour phase technology for decontaminating materials. The work is the third phase of the testing, and it feeds a continuing research programme for Sellafield. The phase covers technical work on the process as well as testing it.
The laboratory awarded the £102,902 contract directly, without competition. It runs from April 2026 to March 2027.
Contract ends March 2027
- What
- Nuclear technical support, engineering and safety
- Value
- £102,902
- How it was bought
- Below threshold - without competition
- Dates and next
- Apr 2026 to Mar 2027