Trident Maintenance paints Battlehill Estate Phase 5 for North Tyneside
- North Tyneside Council
- North East
- Call-off
- 6 October 2025 to 6 November 2025
North Tyneside Council hired Trident Maintenance Services Ltd to paint the inside of homes in Phase 5 of the Battlehill Estate project. The job was set to last one month.
The council chose Trident through a mini competition under its Contract 13 Internal Painting & Decorating including Minor Repairs framework. The £33,000 contract ran from October 2025 and was due to end in November 2025.
- What
- Painting and decorating
- Supplier
- Trident Maintenance Services Ltd
- Value
- £33,000
- How it was bought
- Call-off, North Tyneside Council
- Dates and next
- Oct 2025 to Nov 2025