Thomas Armstrong rebuilds Holme Beck Path wall for North Yorkshire
- North Yorkshire Council
- Yorkshire and the Humber
- Below threshold - limited competition, 2 bids
- 31 July 2026 to 18 September 2026
North Yorkshire Council hired Thomas Armstrong (Construction) Ltd, a small business, to rebuild the masonry retaining wall along Holme Beck Path. The work was to rebuild the masonry and make the path's boundary wall sound again.
The council ran a limited competition and received two bids. Thomas Armstrong won the £82,949 contract in July 2026, and the work was due to end in September 2026.
- What
- Retaining walls, slope stabilisation and land hazard works
- Value
- £82,949
- How it was bought
- Below threshold - limited competition
- 2 bids
- Dates and next
- Jul 2026 to Sep 2026