Strategic Flood Risk Assessment for North Yorkshire goes to JBA Consulting
- North Yorkshire Council
- Yorkshire and the Humber
- Restricted procedure
- 2 September 2026 to 31 October 2029
North Yorkshire Council hired JBA Consulting to prepare a Strategic Flood Risk Assessment for planning across York and North Yorkshire.
JBA Consulting is producing a Level 1 assessment, with a Level 2 assessment added where it is required. The work must comply with the National Planning Policy Framework and National Planning Practice Guidance. It will inform the York and North Yorkshire Combined Authority's spatial development strategy. It will also inform local plans for North Yorkshire Council, City of York Council and the North York Moors and Yorkshire Dales National Park Authorities.
The £50,000 contract followed a restricted tender. It runs from September 2026 to October 2029.
Contract ends October 2029
- What
- Local plan evidence base studies
- Supplier
- JBA Consulting
- Value
- £50,000
- How it was bought
- Restricted procedure
- Dates and next
- Sep 2026 to Oct 2029