Dounreay Steam Line Contingency piping comes from JGC Engineering
- Nuclear Restoration Services
- North West
- Direct
- 7 April 2026 to 30 November 2026
Nuclear Restoration Services hired JGC Engineering and Technical Services Ltd to source, build and commission temporary piping at Dounreay.
The pipework carries steam and feedwater, plus drainage, for five packaged lines. It links the tie-in points to a package boiler set up outside. The job is the second phase of the site's Steam Line Contingency.
NRS awarded the eight-month, £997,722 contract directly in April 2026. It could run to November 2027 to allow for changes to the scope or conditions outside either party's control.
Contract ends November 2026
- What
- Industrial and process mechanical services
- Value
- £997,722
- How it was bought
- Direct
- Dates and next
- Apr 2026 to Nov 2026
- Option to Nov 2027