HPA RCA Welfare Facility at Hinkley Point goes to Turnbull Infrastructure
- Nuclear Restoration Services
- South West
- Call-off from a dynamic purchasing system
- 19 January 2026 to 28 February 2027
Nuclear Restoration Services (NRS) ordered the HPA RCA Welfare Facility at the Hinkley Point site from Turnbull Infrastructure & Utilities Ltd.
The facility gives site staff welfare amenities for work in a radiologically controlled area. Turnbull is to design, supply and install it, and NRS placed the order through a dynamic purchasing system.
The £2.02m works contract runs from January 2026 to February 2027.
Contract ends February 2027
- What
- Welfare units and portable cabins
- Value
- £2.02m
- How it was bought
- Call-off from a dynamic purchasing system
- Dates and next
- Jan 2026 to Feb 2027