Portfolio management support for Nuclear Restoration Services goes to AMS
- Nuclear Restoration Services
- North West
- Call-off from a framework agreement
- 7 September 2026 to 31 March 2027
Nuclear Restoration Services (NRS) hired Alexander Mann Solutions (AMS) to build a single portfolio management capability across the organisation. The order is part of NRS Delivery Phase 2.
Among other things, AMS assesses how mature the PMO is, models whole-life costs and benchmarks the portfolio. It also sets up governance and assurance for the portfolio. The aim is better investment decisions and more consistency between NRS sites.
AMS took the £1.2m order through a framework in September 2026. It runs to March 2027.
Contract ends March 2027
- What
- Programme management and delivery support (PMO)
- Supplier
- Alexander Mann Solutions (AMS)
- Value
- £1.2m
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Sep 2026 to Mar 2027