Prototype Fast Reactor store fire risk assessment goes to Mott MacDonald
- Nuclear Restoration Services
- Scotland
- Call-off from a framework agreement
- 11 August 2026 to 28 October 2026
Nuclear Restoration Services hired Mott MacDonald to produce a deterministic fire risk assessment. The assessment supported the new Prototype Fast Reactor Alkali Metal Store Safety Case.
Nuclear Restoration Services called the work off a framework in August 2026. The £42,600 contract covered about two months of work and was due to end in October 2026.
- What
- Nuclear technical support, engineering and safety
- Supplier
- Mott MacDonald
- Value
- £42,600
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Aug 2026 to Oct 2026