Breathe Energy designs and installs heat pumps at St Nicholas Hospital
- NTW Solutions Limited
- North East
- Call-off from a framework agreement
- 5 January 2026 to 31 March 2027
NTW Solutions Limited hired Breathe Energy Limited for a de-steaming and heat pump project at St Nicholas Hospital.
The new plant is to provide heating and hot water for buildings around the hospital site. Breathe Energy carries the work from detailed design to handover, including commissioning the system.
The £5.7m contract was placed under a framework agreement and runs from January 2026 to March 2027.
Contract ends March 2027
- What
- Heat pumps
- Supplier
- Breathe Energy Limited
- Value
- £5.72m
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Jan 2026 to Mar 2027