Dungeness A boiler removal and demolition goes to Aureos
- Nuclear Restoration Services
- South East
- Competitive procedure with negotiation (above threshold)
- 23 October 2026 to 4 August 2031
Nuclear Restoration Services has hired Aureos to clear hazards and demolish buildings at Dungeness A, a nuclear power station in Kent, on Romney Marsh. The station stopped generating in 2006 and is being decommissioned.
As principal contractor, Aureos removes asbestos and soft strips the buildings before lifting out eight boilers. Each is about 7m across and 21m long and weighs roughly 700 tonnes. Bypass ducts and sections of the main gas duct go too. The Blower Halls and Central Control Block come down to slab level, and about 30% of the buildings on site will be removed. The contractor also carries out site surveys, including ground and ordnance checks, and remediates the site.
The contract was awarded in October 2026 after a competition with negotiation. It is worth £190.6m and runs to August 2031.
Contract ends August 2031
- What
- Demolition and soft strip
- Supplier
- Aureos
- Value
- £190.6m
- How it was bought
- Competitive procedure with negotiation (above threshold)
- Dates and next
- Oct 2026 to Aug 2031