PFR recladding for Nuclear Restoration Services goes to AJ Engineering
- Nuclear Restoration Services
- North West
- Below threshold - limited competition
- 8 July 2026 to 14 September 2027
Nuclear Restoration Services hired AJ Engineering & Construction Services to replace cladding on the Steam Generator Building and the DA Tower at PFR.
On the Steam Generator Building, the east wall gets new cladding at high and low level and loses redundant glazing structures. The north wall is reclad too, as is the east elevation of the DA Tower.
The contract went to AJ Engineering after a limited competition. Worth £2.2m, it runs for 14 months from July 2026 to September 2027.
Contract ends September 2027
- What
- External wall cladding replacement and overcladding
- Value
- £2.21m
- How it was bought
- Below threshold - limited competition
- Dates and next
- Jul 2026 to Sep 2027