RVA Engineering studies asbestos removal in Wylfa's Turbine Hall
- Nuclear Restoration Services
- North West
- Direct
- 8 January 2026 to 31 March 2026
Nuclear Restoration Services hired RVA Engineering Solutions Limited to study how asbestos could be removed from the Turbine Hall at Wylfa.
The feasibility study assessed the hazards particular to the site and the engineering the removal would need. Its findings were to inform plans for decommissioning the facility. The work formed part of Strategic Enablers.
The £21,500 contract was awarded directly, without a competition, and was due to end in March 2026.
- What
- Asbestos management and consultancy
- Value
- £21,500
- How it was bought
- Direct
- Dates and next
- Jan 2026 to Mar 2026