Harte Demolition clears four staff blocks at Hinchingbrooke Hospital
- North West Anglia NHS Foundation Trust
- East of England
- Below threshold - open competition
- 3 July 2026 to 28 June 2027
Harte Demolition is clearing four staff accommodation blocks at Hinchingbrooke Hospital for North West Anglia NHS Foundation Trust. The work is part of the Hinchingbrooke Hospital Redevelopment Project.
The job runs in two phases. Albert House and St Nicholas House, two-storey terraced blocks, were due down by 18 June 2026. Alexandra House and Victoria House must follow by 13 May 2027. The contractor caps the services, clears and levels the site, and must keep the Treatment Centre and Theatre Block running. The trust plans temporary car parking on the cleared ground.
In an open tender, technical answers counted for 50% of the score, price for 40% and social value for 10%. The trust estimated the work at £950,000 and awarded the contract for £263,476, less than a third of that. The contract runs to June 2027.
Contract ends June 2027
- What
- Demolition and soft strip
- Supplier
- Harte Demolition
- Value
- £263,476
- How it was bought
- Below threshold - open competition
- Dates and next
- Jul 2026 to Jun 2027