Clarke Energy upgrades Cardiff and Vale health board's CHP plant
- NHS Wales Shared Services Partnership
- Wales
- Direct
- 10 December 2025 to 31 March 2026
NHS Wales Shared Services Partnership hired Clarke Energy Limited to overhaul a combined heat and power (CHP) unit for Cardiff and Vale University Health Board. Alongside the 90,000-hour service, the unit was to get the latest XT4 control system and a new radiator cooling system. Every energy meter was to be replaced too.
Both of the health board's CHP units had passed 90,000 running hours without an overhaul in 16 years, and breakdown was becoming more likely. The board planned to upgrade one and run the other at a lower load.
Clarke Energy, the original equipment manufacturer, had recently been given the maintenance contract as the only provider able to do such specialised work. The £560,000 upgrade was awarded to it directly. It was due to end in March 2026.
- What
- CHP and energy centre maintenance
- Supplier
- Clarke Energy Limited
- Value
- £560,000
- How it was bought
- Direct
- Dates and next
- Dec 2025 to Mar 2026