Drivetrain test facility upgrade design goes to Ryder Architecture
- Offshore Renewable Energy Catapult
- North East
- Direct award
- 26 September 2026 to 31 January 2027
Offshore Renewable Energy Catapult hired Ryder Architecture Limited for the RIBA Stage 4 design of its drivetrain test facility upgrade.
Ryder develops the detailed design across architecture and the other disciplines involved. That gives the catapult the detail it needs to procure and build the upgrade.
The catapult awarded the £659,392 contract directly, without a competition. It runs from September 2026 to January 2027.
Contract ends January 2027
- What
- Architectural design services
- Supplier
- Ryder Architecture Limited
- Value
- £659,392
- How it was bought
- Direct award
- Dates and next
- Sep 2026 to Jan 2027