Contract awardedFire engineering and fire strategy

Part B Group leads fire engineering on five Orbit high-risk buildings

Orbit Group Limited appointed Part B Group Ltd, a small business, as fire engineer for improvement projects at five high-risk buildings.

The buildings are Bosworth House, Carrack House, Becton Place, Saxon House and St Annes Quarter. Part B Group leads the design and pre-construction stages, and handles design questions for the rest of each project.

Part B Group was the only bidder, with the award decided on lowest price. The award was £455,000 in June 2026.

What
Fire engineering and fire strategy
Value
£455,000
How it was bought
Not published
1 bid
Dates and next
18 Jun 2026

How it was bought

1 official notice
  1. 19 Jun 2026Award noticeFind a Tender

How it compares

With every fire engineering and fire strategy award since 2021

Half of awards fall between £28,938 and £99,009Median £52,033

Awards
252
Firms that won them
112
Median award
£52,033
of 242 with a value
This award
Bigger than 94%
of them
Typical length
1 year

Part B Group Ltd ranks 4th of 112 firms for fire engineering and fire strategy awards since 2021.

RankFirmAwardsValue
1Locked24£1.09m
2Locked13£1.19m
3Locked10£2.98m
4Part B Group Ltd Won this one9£1.16m
5Locked8£704,735
5Locked8£423,985
See who wins this work

Figures to 21 November 2026

Fire engineering and fire strategy at other buyers

Orbit Group Limited has awarded 151 contracts since 2021.

See Orbit Group Limited's page
  • Part B Group Ltd has won 16 public contracts since 2021.

1 fire engineering and fire strategy tender is open now

See it