Offshore Renewable Energy Catapult hired D Hall Renewables Ltd to rotate wind turbine blades so that urgent blade repairs can start.
The work comes as two separate rotations, spread over weeks. For each one, D Hall Renewables brings the cranes and lifting specialists, backed by technicians.
The catapult awarded the £96,000 contract directly, without a competition, in November 2026. It is due to end in January 2027.
Contract ends January 2027
- What
- Crane hire and contract lifting
- Supplier
- D Hall Renewables Ltd
- Value
- £96,000
- How it was bought
- Below threshold - without competition
- Dates and next
- Nov 2026 to Jan 2027