Prior+Partners draws up Oxfordshire's Banbury 2050 Vision Masterplan
- Oxfordshire County Council
- South East
- Limited
- 1 April 2026 to 31 March 2027
Oxfordshire County Council hired Prior+Partners to produce the Banbury 2050 Vision Masterplan for the town.
The work has three parts. A spatial framework plan will set priorities for growth and investment in Banbury. An investment prospectus aims to raise the town's profile and attract investment. A delivery plan will map how the vision is funded and carried out, and with which partners.
The £157,983 contract was awarded in March 2026. It runs for a year, and a six-month extension could take it to September 2027.
Contract ends March 2027
- What
- Masterplanning, urban design and design codes
- Supplier
- Prior+Partners
- Value
- £157,983
- How it was bought
- Limited
- Dates and next
- Apr 2026 to Mar 2027
- Option to Sep 2027