Contract awardedGround investigation

ERS wins ground investigation for the Craigie Burn flood protection scheme

Perth & Kinross Council hired ERS to investigate the ground along the Craigie Burn in Perth, where the council is developing a flood protection scheme.

The work includes exploratory trial pits. Its findings will inform the scheme, which covers sections of the burn.

Two bids came in, and the council awarded ERS the £40,924 contract in August 2026.

What
Ground investigation
Supplier
ERS
Value
£40,924
How it was bought
Not published
2 bids
Dates and next
10 Aug 2026

How it was bought

1 official notice
  1. 23 Oct 2026Award noticePublic Contracts Scotland

Perth & Kinross Council has bought this 3 times since 2021

Last bought
Aug 2026
Typical length
3 months
Typical value
£97,166
Suppliers used
3
AwardedContractWon byValue
Aug 2026This purchaseERS£40,924
Apr 2025Locked3 monthsLocked£199,999
Dec 2022Locked2 monthsLocked£97,166

Suppliers Perth & Kinross Council has used

SupplierContractsValue
Locked1£199,999
Locked1£97,166
ERS Won this one1£40,924
See the contracts and who won them

Figures to 21 November 2026

How it compares

With every ground investigation award since 2021

Half of awards fall between £30,949 and £170,315Median £68,549

Awards
604
Firms that won them
198
Median award
£68,549
of 571 with a value
This award
Smaller than 66%
of them
Typical length
4 months
In Scotland
51 awards

ERS ranks 53rd of 198 firms for ground investigation awards since 2021.

RankFirmAwardsValue
1Locked44£1.77m
2Locked30£47.4m
3Locked29£2.6m
4Locked25£6.53m
5Locked16£3.15m
5Locked16£2.53m
53ERS Won this one2£120,713
See who wins this work

Ground investigation at other buyers

Perth & Kinross Council has awarded 896 contracts since 2021.

See Perth & Kinross Council's page
  • ERS has won 16 public contracts since 2021.

3 ground investigation tenders are open now

See them
More ground investigation contracts awarded in 2026