Air compressor maintenance at The Pirbright Institute goes to PSI ACB
- The Pirbright Institute
- South East
- Open procedure, 7 bids
- 1 August 2026 to 31 July 2029
The Pirbright Institute is paying Gardner Denver Ltd ta PSI ACB £141,746 to service its compressed air systems, little more than half its estimate. The institute had put the work at about £249,555.
Each compressor gets a minor and a major service every year, to the manufacturers' standards. The kit includes machines made by Atlas Copco, CompAir and Hydrovane. Backup compressors and receivers must keep air flowing while units are serviced, and visits are fitted around the institute's planned building shutdowns. Engineers need security clearance to work unescorted, and critical assets have a four-hour emergency response target.
Seven bids came in, scored equally on price and quality. The contract was awarded in July 2026 and runs to July 2029, with an optional extra year.
Contract ends July 2029
- What
- Compressed air systems
- Supplier
- Gardner Denver Ltd ta PSI ACB
- Value
- £141,746
- How it was bought
- Open procedure
- 7 bids
- Dates and next
- Aug 2026 to Jul 2029
- Option to Aug 2030