The Pirbright Institute hired Lührfilter to rewrite the control software for the incinerator in its Brooksby Building. The incinerator works across the building's containment barrier. The Brooksby Building could not be used for SAPO4 work, or meet its licensing conditions, until the incinerator ran reliably on its own. A full rewrite would also let Pirbright understand, run and look after the incinerator safely.
The job covered the PLCs for the main, hydraulic and bin lifter systems, the SCADA software and new HMI screens for the hydraulics. It also took in hot commissioning, operational testing and staff training.
The institute awarded Lührfilter the £248,900 contract directly in May 2026, and it was due to end in October 2026.
- What
- Industrial control, SCADA and telemetry systems
- Supplier
- Lührfilter
- Value
- £248,900
- How it was bought
- Direct award