Plymouth City Council hired Chubb Electrics Ltd for specialist electrical and mechanical maintenance of the leachate treatment works at Chelson Meadow, a landfill site. The work covered the treatment plant and three leachate pumping stations, with both routine servicing and repairs when faults arose.
The £15,000 contract ran from October 2025 and was due to end in March 2026.