Heat network consultancy for Plymouth City Council comes from Buro Happold
- Plymouth City Council
- South West
- Below threshold - without competition
- 1 October 2026 to 12 December 2027
Plymouth City Council hired Buro Happold for technical advice on linking council buildings to a heat network that is yet to be built.
Buro Happold works alongside the Heat Network Development Partner the council has already appointed. The firm builds business cases for connecting the buildings, studies feasibility and connections and looks at the rules that apply. It also gives technical assurance and helps with commercialisation.
The council awarded the work directly in October 2026, without a competition. The £103,250 contract runs to December 2027.
Contract ends December 2027
- What
- Local area energy planning and energy infrastructure feasibility
- Supplier
- Buro Happold
- Value
- £103,250
- How it was bought
- Below threshold - without competition
- Dates and next
- Oct 2026 to Dec 2027