Pitch borehole and pump for Royal Holloway come from Nicholls Countryside
- Royal Holloway, University of London
- South East
- Below threshold - without competition
- 13 July 2026 to 8 January 2027
Royal Holloway, University of London is paying Nicholls Countryside Construction to drill a borehole and install a pump for its sports pitches.
The pump is there to draw groundwater from the borehole so the university can water the pitches.
The university awarded the £68,883 contract directly, without a competition. The work runs from July 2026 to January 2027.
Contract ends January 2027
- What
- Irrigation systems supply, installation and maintenance
- Value
- £68,883
- How it was bought
- Below threshold - without competition
- Dates and next
- Jul 2026 to Jan 2027