HMS Victory shipwright support goes to T Nielsen & Co
- National Museum of the Royal Navy
- South East
- Direct award
- 22 June 2026 to 31 July 2026
The National Museum of the Royal Navy hired three shipwrights from T Nielsen & Co Limited for conservation of HMS Victory's port side frames.
The HMS Victory Conservation Project expected a nine-month delay to the port side frames. Five and a half weeks of extra shipwright time was meant to make up part of it. The project put the cost at £42,230, including a £6,480 contingency equal to a week's work.
The museum awarded the contract directly, at £35,750 before VAT, for work in June and July 2026.
- What
- Vessel and boat maintenance, repair and refit
- Supplier
- T Nielsen & Co Limited
- Value
- £35,750
- How it was bought
- Direct award
- Dates and next
- Jun 2026 to Jul 2026