Rutland Local Area Energy Plan goes to Energy Systems Catapult
- Rutland County Council
- East Midlands
- Open
- 9 December 2025 to 21 October 2027
Rutland County Council hired Energy Systems Catapult to draw up a Local Area Energy Plan (LAEP) for Rutland.
The plan maps how Rutland could reach a net-zero energy system by 2050. It looks at heat, electricity and transport, both today's needs and those to come, and sets out the most cost-effective ways to decarbonise. A plan of this kind can improve the council's chances of attracting outside funding and private investment, and it informs choices on housing, transport and planning.
Quality counted for 70% of the score and price for 30%. The £89,955 contract runs from December 2025 to October 2027.
Contract ends October 2027
- What
- Local area energy planning and energy infrastructure feasibility
- Supplier
- Energy Systems Catapult
- Value
- £89,955
- How it was bought
- Open
- Dates and next
- Dec 2025 to Oct 2027