Salisbury NHS Foundation Trust awarded Westmade Limited £933,647 to take down one of the steel chimney stacks at Salisbury District Hospital. That was more than one and a half times the £510,000 estimate.
The stacks stood in an internal courtyard with no vehicle access and rose about 38 metres above the main plant room. They were built around 1988. Removing the eastern stack meant shutting down the main plant and running temporary boiler and generator plant meanwhile. The generator flues had to be rerouted, and the CHP unit and Boiler 3 were to stay isolated.
The works followed appraisal studies by Mott MacDonald and were funded by NHS Estates Safety Funding 2025/26. Westmade was chosen after an open tender. The contract ran from April 2026 and was due to end in August 2026.
- What
- Demolition and soft strip
- Supplier
- Westmade Limited
- Value
- £933,647
- How it was bought
- Below threshold - open competition
- Dates and next
- Apr 2026 to Aug 2026