Safe & Warm Grassroot Community Scheme is delivered by CSE
- Scotia Gas Networks Limited
- Direct award
- 3 August 2026 to 31 March 2028
Scotia Gas Networks is paying the Centre for Sustainable Energy (CSE) to build a community network protecting households at risk of fuel poverty.
CSE will find trusted grassroots organisations across the gas distribution network areas and train them to offer energy support and referrals, with a mentor network to keep those skills going.
CSE, a small business, was awarded the £1.15m contract directly in April 2026. It runs to March 2028.
Contract ends March 2028
- What
- Voluntary and community sector infrastructure support
- Supplier
- Centre for Sustainable Energy
- Value
- £1.15m
- How it was bought
- Direct award
- Dates and next
- Aug 2026 to Mar 2028