Contract awardedRail depot plant and equipment
CET repairs at SE Trains' Ramsgate and Ashford depots go to Depot Rail
- SE Trains Limited
- South East
- Direct
- 16 March 2026 to 16 March 2027
SE Trains Limited has hired Depot Rail Limited to repair and refurbish the controlled emission toilet (CET) systems at its Ramsgate and Ashford depots. The work is upkeep of sanitation equipment in a working rail setting.
SE Trains awarded the £108,920 contract directly. It runs for a year from March 2026, and a six-month contingency extension could take it to September 2027.
Alert me to similar tenders
Contract ends March 2027
- What
- Rail depot plant and equipment
- Buyer
- SE Trains Limited
- Supplier
- Depot Rail Limited
- Value
- £108,920
- How it was bought
- Direct
- Dates and next
- Mar 2026 to Mar 2027
- Option to Sep 2027