Amentum excavates and pours the HEx-1 laydown area for Sellafield
- Sellafield Ltd
- North West
- Call-off from a framework agreement
- 9 September 2026 to 1 May 2028
Sellafield Ltd has hired Amentum Clean Energy to prepare the HEx-1 laydown area. The works cover excavating the area and then the pour that follows.
Sellafield ordered the job as a call-off from a framework agreement in September 2026. The contract is worth £3,425,940 and runs for 20 months, to May 2028.
Contract ends May 2028
- What
- Groundworks, enabling works and site infrastructure
- Buyer
- Sellafield Ltd
- Supplier
- Amentum Clean Energy
- Value
- £3.43m
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Sep 2026 to May 2028