St Leger Homes of Doncaster (SLHD) hired R. H. Fullwood & Co Ltd, a small business, to add building and repair capacity to its in-house team.
SLHD's Direct Labour Organisation handles the common responsive repairs. Fullwood takes on standard work when the team needs more hands, and non-standard jobs outside the usual repair cycle that count as specialist. Quality made up 40% of the score, price 50% and social value 10%.
Eight bids came in. The £6.1m contract runs to June 2028, with two optional one-year extensions to June 2030.
Contract ends June 2028
- What
- Housing responsive repairs
- Supplier
- R. H. Fullwood & Co Ltd
- Value
- £6.13m
- How it was bought
- Open procedure
- 8 bids
- Dates and next
- Jun 2026 to Jun 2028
- Option to Jun 2030